Construction update North Dragon October 2014
The construction of North Dragon is progressing according to schedule. See below the Heli-deck assembling and the Front Starboard view of pontoons and columns
This author has not written his bio yet.
But we are proud to say that Marianne Thompson contributed 57 entries already.
The construction of North Dragon is progressing according to schedule. See below the Heli-deck assembling and the Front Starboard view of pontoons and columns
Steel Cutting of Beacon Atlantic took place at the CIMC Yantai Raffles yard on 17 June 2014 according to plan.
Project Kick Off meetings were held in January 2014 and the first batch of drawings are being prepared for DnV approval. All major long lead items have been ordered by the shipyard.
Planned Achieved Steel Cutting (SC) 20 Aug 2013 28 June 2013 Block Fabrication Start (BF) 26 Aug 2013 15 Aug 2013 Block Erection Start (BE) 26 Dec 2013 26 Dec 2013 Keel Laying Block erection start
http://offshore.no/sak/60553_bygger_rigg_for_norske_forhold
YCRO has secured an order from Beacon Holdings Group Ltd. (The Owner) to build one unit of harsh environment ice class semi-submersible drilling rig. The rig will be named the Beacon Atlantic.