Construction update North Dragon October 2014

The fabrication of North Dragon is progressing according to schedule.  The construction of North Dragon is progressing according to schedule. See below the Heli-deck assembling and the Front Starboard view of pontoons and columnsFront strtboard view oct 14 Heli-deck assembling ongoing oct 14

Fabrication continuing on both the pontoons and the deck box

Planned
 Achieved
Steel Cutting (SC) 20 Aug 2013  28 June 2013
Block Fabrication Start (BF) 26 Aug 2013 15 Aug 2013
Block Erection Start (BE) 26 Dec 2013 26 Dec 2013
Keel Laying       Block erection start

Read more

Steel Cutting North Dragon 27.06.13

steel cutting ND NSR YARDsteel cutting ND NSR team