Beacon Atlantic – Wheelhouse and main deck
Beacon Atlantic wheelhouse and main deck. Great progress in the preparation for painting and the installation of the wheelhouse windows.
Mating of Beacon Atlantic 29.11.2015
The mating of Beacon Atlantic was successfully done 29.11.2015.
Beacon Atlantic Lower Hull is floating free
The Beacon Atlantic lower hull was successfully floated off the barge 22.10.2015.
Launching of the Beacon Atlantic hull – 12.10.15
Today marked the successful launching of the Beacon Atlantic hull. The hull was launched on schedule and will be ready for the mating with the deck box in November. Congratulations to both project teams for achieving this very important milestone.
Project lower hull lifted successfully
Last hull block for Beacon Atlantic lifted into position on 2 June 2015 according to schedule
Steel Cutting Beacon Atlantic
Steel Cutting of Beacon Atlantic took place at the CIMC Yantai Raffles yard on 17 June 2014 according to plan.
Project had Effective Date on the 31st December 2013
Project Kick Off meetings were held in January 2014 and the first batch of drawings are being prepared for DnV approval. All major long lead items have been ordered by the shipyard.
Project had Effective Date on the 31st December 2013. Project Kick Off meetings were held in January 2014 and the first batch of drawings are being prepared for DnV approval. All major long lead items have been ordered by the shipyard